Early 2026 – Contractor chosen and brought on board
April 2026 – Test pits, materials, and strategy coming into focus
May 2026 – Stukel contract finalized and project goes out to bid with sub-contractors
Summer and Fall 2026 – Office wing will be built
Fall 2026 – Elevator addition will be built
Throughout – Internal upgrades to mechanical, electrical, plumbing, HVAC, accessibility, fire safety, and all areas affected by additions.
February 2027 – Occupancy certificates
March 2027 – Projected completion